This year’s Pavement Reconstruction Project is Phase III and will include reconstruction of 10 street segments.





Alderbrook PlaceFernwood DriveNorth EndSurface Reconstruct:
Remove 4 inches AC/AB Replace with 4 inches Hot Mix Asphalt (HMA)
Chalda Way225ft N/O Williams DriveRheem BoulevardSurface Reconstruct:
Remove 3 inches" AC/AB Replace with 3 inches HMA
Country Club DriveSouthard CourtSandringham SouthSurface Reconstruct:
Remove 4 inches AC/AB Replace with 2 inches HMA and 2 inches Rubberized Hot Mix Asphalt (RHMA)
Del Monte CourtCarter DriveWest EndSurface Reconstruct:
Remove 4 inches AC/AB Replace with 2 inches HMA and 2 inches RHMA
Del Monte WayCarter DriveSouth EndSurface Reconstruct:
Remove 5 inches AC/AB Replace with 3 inches HMA and 2 inches RHMA
Harold DriveRheem BoulevardSouth EndSurface Reconstruct:
Remove 4 inches AC/AB Replace with 2 inches HMA and 2 inches RHMA
Marie PlaceLarch AvenueWest EndSurface Reconstruct:
Remove 4 inches AC/AB Replace with 4 inches HMA
Natalie DriveBuckingham DriveCampolindo DriveSurface Reconstruct:
Remove 4 inches AC/AB Replace with 2 inches HMA and 2" RHMA
Scofield DriveGoodfellow DriveRheem BoulevardSurface Reconstruct:
Remove 4 inches AC/AB Replace with 2 inches HMA and 2" RHMA
Winslow PlaceCorliss DriveNorth EndSurface Reconstruct:
Remove 5 inches AC/AB Replace with 5 inches HMA