2021 (2022) Street Resurfacing Project - Phase 2
Road Closure Alert for Residential Road Construction - Thursday, July 7, 2022.
There will be several residential Road Closures for road construction on Thursday, July 7, 2022. The microsurfacing operation will affect street access for several hours, except for emergency vehicles. For questions or concerns, please contact the Public Works Department at 925-888-7026.
Pavement resurfacing will occur on:
- Via Granada,
- Archer Circle,
- Ashford Place,
- Fleuti Drive, and
- Selborne Way.
PLEASE NOTE: No vehicles will be allowed on these streets for several hours during the day. If you need to come or go during the day, please plan to park your vehicle on an adjacent street. Pedestrian access may also be limited in some circumstances.
Construction Inspector: Patrick Giles (925) 998-7937
Road Closure Alert for Residential Road Construction - Thursday, June 30, and Friday, July 1, 2022.
There will be several residential Road Closures for road construction on Thursday, June 30, and Friday, July 1, 2022. Pavement resurfacing will occur on Via Granada, Amberwood Court, Archer Circle, Ashford Place, Augusta Drive, Cypress Point Way, Country Club Drive, Fernwood Drive, Fleuti Drive, and Selborne Way. The microsurfacing operation will affect street access for several hours, except for emergency vehicles. For questions or concerns, please contact the Public Works Department at 925-888-7026.
Notification Letter - 6-27-2022
Road Closure Alert for Cypress Point Way on Thursday, June 23, 2022.
The bulb of the cul-de-sac of Cypress Point Way will be chip sealed on Thursday, June 23 approximately between the hours of 9:00 AM and 1:00 PM, and will temporarily affect access to addresses 163 through 192 Cypress Point Way. Please also note the revised schedule below for the second phase of the street resurfacing project. Thank you for your patience during this important Town project.
Road Closure Alert for Residential Road Construction (Modified Road Closure and Construction Schedule)
Please note the following UPDATED & REVISED construction schedule:
Street and Limits of Work | Chip Seal | Micro-surfacing | |
Via Granada Corte Del Sol to Calle La Mesa | Date NA | Date 01-July | |
Archer Circle Woodside Drive to End | Date 15-Jun | Date 01-July | |
Ashford Place Corliss Drive to End | Date 15-Jun | Date 01-July | |
| Date 15-Jun | Date 30-Jun | |
Country Club Drive St. Andrews Dr. to School St. (East Bound Only) | Date NA | Date 30-June & 01-July | |
Cypress Point Way St. Andrews Drive to End | Date 15-Jun | Date 30-Jun | |
Augusta Drive (AM/PM Split) St. Andrews to 785 Augusta Drive at crosswalk. | Date NA | Date 01-July | |
Fleuti Drive Sanders Drive to End | Date 15-Jun | Date 01-July | |
Selborne Way (East) Oxford Drive to Beginning of Bulb | Date 15-Jun | Date 01-July | |
Amberwood Court Larch Avenue to Beginning of Bulb | Date 15-Jun | Date 01-July |
Street parking will be prohibited. Please look for "No Parking'' signs posted on barricades specifying the dates and hours of restricted parking, as cars may be towed if they are parked in restricted areas. Please also make sure any front yard sprinklers are turned off the day of the operation.
If the dates correspond to your usual trash pickup day, please note that waste pickup will not be affected. Please continue to put your waste bins out as you normally do on waste pickup day.
Please continue to visit the Town’s website for additional information and updates. If, for any reason, the work is not able to be performed on the scheduled days, new notices will be placed a minimum of two working days prior to the rescheduled work.
This is a very important project for the Town, and we greatly appreciate your patience! Please contact Public Works if you have any questions or concerns at (925) 888-7026.
Construction Manager: Patrick Giles (925) 998-7937
Road Closure Alert for Residential Road Construction
On Wednesday, June 15, 2022, the first phase of pavement resurfacing will take place.
This first phase includes what is called an Asphalt Rubber Chip Seal consisting of a hot spray application of a rubberized asphalt binder followed by a layer of aggregate. The application provides a flexible, waterproof wearing surface that seals the existing pavement and is height resistant to cracking. Note that not all streets in the project will be receiving the chip seal.
This first phase includes what is called an Asphalt Rubber Chip Seal consisting of a hot spray application of a rubberized asphalt binder followed by a layer of aggregate. The application provides a flexible, waterproof wearing surface that seals the existing pavement and is height resistant to cracking. Note that not all streets in the project will be receiving the chip seal. (See revised dates in red below).
Street and Limits of Work | Chip Seal | Micro-surfacing | |
Via Granada Corte Del Sol to Calle La Mesa | Date NA | Date 01-July | |
Archer Circle Woodside Drive to End | Date 15-Jun | Date 01-July | |
Ashford Place Corliss Drive to End | Date 15-Jun | Date 01-July | |
| Date 15-Jun | Date 29-Jun | |
Country Club Drive St. Andrews Dr. to School St. (East Bound Only) | Date NA | Date 29-June & 01-July | |
Cypress Point Way St. Andrews Drive to End | Date 15-Jun | Date 29-Jun | |
Augusta Drive (AM/PM Split) St. Andrews to 785 Augusta Drive at crosswalk. | Date NA | Date 01-July | |
Fleuti Drive Sanders Drive to End | Date 15-Jun | Date 01-July | |
Selborne Way (East) Oxford Drive to Beginning of Bulb | Date 15-Jun | Date 01-July | |
Amberwood Court Larch Avenue to Beginning of Bulb | Date 15-Jun | Date 01-July |
Street parking will be prohibited during both operations. Please look for "No Parking'' signs posted on barricades specifying the dates and hours of restricted parking, as cars may be towed if they are parked in restricted areas. Please also make sure any front yard sprinklers are turned off the day of the operation.
Please note that waste pickup will not be affected. Please continue to put your waste bins out as you normally do on waste pickup day.
Please continue to visit the Town’s website for additional information and updates. If, for any reason, the work is not able to be performed on the scheduled days, new notices will be placed a minimum of two working days prior to the rescheduled work.
This is a very important project for the Town, and we greatly appreciate your patience! Please contact Public Works if you have any questions or concerns at (925) 888-7026.
2021 (2022) Street Repair Project - Phase 2
Design and bidding for Phase 2 of the 2021 Pavement Resurfacing Project (21-401) have begun. While Phase 1 consisted of localized asphalt repairs and was completed in 2021, Phase 2 will consist of resurfacing the streets that received repairs.
Project Team:
Construction Manager: Patrick Giles (925) 998-7937
The current list of streets that will be resurfaced is as follows:
Town of Moraga 2021 (2022) Street Resurfacing Project Phase 2 - Street List | ||
Street Name | Start | End |
Agusta Drive | Saint Andrews Drive | 1450 ft S/O Saint Andrews Drive |
Amberwood Court | West End | Larch Avenue |
Archer Circle | West End | Woodside Drive |
Ashford Place | Corliss Drive | North End |
Country Club (EB) | Saint Andrews Drive | School Street |
Cypress Point Way | Saint Andrews Drive | East End |
Fernwood Drive | Bedford Place | Newberry Place |
Flueti Drive | Sanders Drive | North End |
Selborne Way East | Oxford Drive | East End |
Via Granada | Calle La Mesa | Corte Del Sol |
Note: during the bidding process, this list may change.
Phase 2 is being done in partnership with the City of Lafayette and Contra Costa County to capitalize on reduced unit pricing for larger overall projects. The bid package is currently available on the City of Lafayette’s website: https://www.lovelafayette.org/city-hall/city-departments/engineering/city-construction-projects/2022-surface-seal-project. Bids are due March 17, 2022, at 2:00 PM.
The Moraga resurfacing plans are available here: https://ca-moraga.civicplus.com/DocumentCenter/View/6696/21-401---MORAGA-2022-STREET-REPAIR-PROJECT
Construction is anticipated to begin in April and be completed by August 2022. Residents will be notified as more accurate schedules become available.
-